A note in clause 4.3 of IEEE C57.12.90-2021 recommends that the dielectric tests come after the tests made at reduced voltage: winding resistance, polarity with phase relation, turns ratio, no-load loss with excitation current, impedance with load loss, and temperature rise.

ProvenanceIEEE C57.12.90-2021 supports data record std.ieee-c57-12-90.test-order, which is cited on the entry IEEE Standard Test Code for Liquid-Immersed Distribution, Power, and Regulating Transformers.SOURCEIEEE C57.12.90-2021IEEE C57.12.90-2021Licensed standard, clause 4.3DATA RECORDstd.ieee-c57-12-90.test-orderstd.ieee-c57-12-90.test-..Verified 2026-10-24ENTRYIEEE Standard Test Code for Liquid-Immersed Distribution, Power, and Regulating TransformersIEEE Standard Test Code ..No revisions
Provenance. Where this record comes from and where it is used: the cited source, the record itself and the entry that cites it.
Provenance: the chain from source to entry.
StepItemDetail
SourceIEEE C57.12.90-2021Licensed standard, clause 4.3
Data recordstd.ieee-c57-12-90.test-orderVerified 2026-10-24
EntryIEEE Standard Test Code for Liquid-Immersed Distribution, Power, and Regulating TransformersNo revisions
Subject
IEEE Standard Test Code for Liquid-Immersed Distribution, Power, and Regulating Transformers (Standards)
Kind
Standard scope
Source
IEEE C57.12.90-2021, clause 4.3, Test Code for Liquid-Immersed Distribution, Power and Regulating Transformers, IEEE.

History

Every recorded change to this data record, oldest first.
DateChange
2026-10-24created
2026-10-24revised
2026-10-24review_status unreviewed -> software_reviewed

Cite this page

Cite the governing standard for the fact itself; cite this page as the finding aid.

"Data record std.ieee-c57-12-90.test-order." Transformer Testing Reference. 2026-10-24. https://www.transformertestingreference.com/data/std.ieee-c57-12-90.test-order/.